Shorter maximum timeframes for smart meter installation?

Twitter
LinkedIn
Facebook

The Federal Government announced on 21 February that it has submitted a rule change request to the Australian Energy Market Commission (AEMC), asking for a maximum timeframe for smart meter installations (see www.environment.gov.au/minister/frydenberg/media-releases/mr20180221.html).

smart meter installation

Photo by jesse orrico on Unsplash

In today’s article, we explain the background and future process for this change.

Smart Meter Installation – Background

With few exceptions, where a new connection to the National Energy Market is set up, or where an existing meter needs replacing, a retailer (through its Metering Coordinator) must replace that meter with a smart meter (National Electricity Rules, 7.8.3).

A smart meter (also known as an ‘advanced’ meter or a ‘type 4’ meter) is a device that digitally measures energy use. Energy data is sent to the retailer automatically, without the need for the meter to be manually read by a meter reader. Other mechanisms included within a smart meter allow for:

  • remote switching power on or off;
  • measuring power quality at the premises;
  • customer monitoring of energy use;
  • notifying the distributor when the power goes out.

While there was previously a requirement to replace new meters within six days, under the current iteration of the rules there is no maximum time limit.

The roll-out of smart meters is one way in which the Government seeks to reduce energy costs for consumers as they allow consumers to keep a closer eye on their energy bill, and retailers to reduce the cost of reading energy usage.

The Federal Government considers that, without a maximum time limit, retailers may be taking longer than is necessary to upgrade the meters.

The Rule Change process

The Federal Government does not have the power to change the National Electricity Rules itself. This is a decision for the AEMC and it will follow the following process:

  • Initial assessment of the proposal. The proponent of the rule change request (who can be anyone) must, in their application, make a statement as to the nature and scope of the issue and how it relates to the National Electricity Objective. That Objective, according to section seven of the National Electricity Law, is to promote efficient investment in, and efficient operation and use of, electricity services for the long-term interests of consumers of electricity with respect to:
  • price, quality, safety and reliability and security of supply of electricity;
  • the reliability, safety and security of the national electricity system.
  • Once the AEMC is satisfied, it will commence the rule change process, seeking submissions on the request;
  • The AEMC will take those submissions into account, and then, if it considers it appropriate, make a draft determination;
  • Stakeholders, if they wish, can then lodge a submission on that draft rule determination;
  • The AEMC can then publish a final rule determination if it considers it appropriate to do so.

We will keep you posted on the progression of any draft rule change and when you will be able to make submissions on it. For any additional advice, please get in touch with us by clicking here.

 

More to explorer

werribee park mansion

Victoria consults on lower prices for embedded network customers

The Victorian Government has opened consultation on proposed pricing reforms for embedded networks, following its announcement that it intends to require lower energy prices for households and small businesses in those networks. The consultation is relevant to residential and small commercial embedded network customers, embedded network operators, exempt sellers and suppliers, licensed retailers operating in embedded networks, owners corporations, retirement villages, caravan parks, shopping centres and providers of bundled energy-related services such as bulk hot water, centralised heating and cooling.

smartphone beside a magnifying glass

Energy Retailer Assurance Audits in 2026: An Australian Guide

Assurance audits used to be a tick-the-box exercise. They are not anymore. With the Australian Energy Regulator (AER) refreshing its Compliance Procedures and Guidelines and releasing an updated Practice Guide for Compliance Audits last year energy retailers in Australia are operating in a sharper, more evidence-driven assurance environment than at any point in the National Energy Retail Law’s history. This post explains, in plain English, what an assurance audit looks like under the current settings, where the AER is looking hardest in 2025/26, and

street road near green and yellow trees

Embracing the uncertainty of rapid advancement and adoption of general artificial intelligence for energy businesses

The way businesses and professionals interact with artificial intelligence has changed. Over the past two months, we have observed a shift across our client base and the broader regulatory and legal community that goes beyond curiosity or experimentation. Professionals who were previously sceptical are now actively engaging with AI tools. Those who were already experimenting are finding that the tools have become materially more capable than they were even six months ago.

Leave a Reply

Your email address will not be published. Required fields are marked *