4 Months not prompt enough to fix customers’ meters

Share on twitter
Twitter
Share on linkedin
LinkedIn
Share on facebook
Facebook

For the failure to promptly fix meters, the AER has issued eight infringement notices which led three AGL retailers to pay a total of 160,000 in penalties. Each infringement notice cost the AGL entities $20,000.

The infringement notices were issued as the AER found that there were sufficient grounds to believe that there was a breach of clause 11.87.7(h) of the National Electricity Rules (NER). The provision requires that a ‘financially responsible Market Participant’ receiving a notice of a metering installation malfunction under clause 11.87.7(g)(3) must ‘promptly appoint a Metering Coordinator’.

Note, Embedded Network Retailers are currently not considered ‘financially responsible Market Participants’. However, if the planned changes by the AEMC come into effect it is likely that the same rules apply to Embedded Network Retailers.

The infringement notices offer some guidance on how the AER interprets the retailer’s obligation to ‘promptly appoint a Metering Coordinator’. In the most significant case, AGL South Australia Pty Ltd appointed a Metering Coordinator 4 months after the infringement notice was issued. The AER found that 4 months to appoint a Metering Coordinator was not reasonable in the circumstances. In other cases the AER found 6 months or 8 months insufficient.

In summary, the infringement notices illustrate that the AER is unlikely to consider 4 months as a reasonable time to appoint a Metering Coordinator to fix customer meters that are faulty. However, this does not mean that an appointment under 4 months will be considered reasonable. Rather the infringement notices illustrate the pressing need for retailers to respond to notices of faulty meters with great urgency.

More to explorer

Eureka tower Melbourne

Victorian Embedded Network ‘ban’: proposed changes to the embedded network regulatory framework in Victoria

On 11 January 2022, the expert panel appointed by the Victorian Government to review the policy position of banning embedded networks in residential settings published its final report. The recommendations, if implemented, will have a significant impact on embedded network operators in Victoria.

The report sets out the panel’s recommendations for implementing a ban and further considers how the ban should apply, or rather what changes should be made to the regulation, to legacy (existing) embedded networks.

Stock market prices

Price Comparisons under the Electricity Retail Code

On 12 January 2022, the Australian Competition and Consumer Commission (ACCC) announced that energy retailer CovaU Pty Ltd had paid $33,300 in penalties arising from three infringement notices issued for alleged contraventions of the Competition and Consumer (Industry Code—Electricity Retail) Regulations 2019 (the Code).

Energy

AEMO Draft 2022 Integrated System Plan review

On 10 December 2021, the Australian Energy Market Operator (AEMO) published the Draft 2022 Integrated System Plan (ISP) (Draft ISP). This was subject to a ‘transparency review’ by the Australian Energy Regulator (AER), released 7 January 2022.  The Draft ISP is now in the consultation stages, prior to final publication in June 2022.

Leave a Reply

Your email address will not be published. Required fields are marked *